REALISATION :    RENOVATION MINERGY-P in ATHENAZ

To be consistent, I couldn't advice others to increase the energy efficiency of their houses without showing the example.

So I have made a total renovation of my home dated 1966 to a low energy comsuption bulding (type Minergy-P). The following works had to be carried out :

  • isolate west, north and south facades with a 30 cm-thick mineral isolation material
  • isolate the separation between heated and non-heated spaces (for example : basement's ceiling, playroom's walls and floor) with 20 cm of Multipor
  • break the balcony thermal bridge (concrete slab sawing and isolation)
  • isolate underground walls up to 1 meter
  • change windows for triple panes
  • create an entrance airlock on the northside
  • install a very low temperature floor heating system
  • install a breakdown double flow with heat recovery
  • build a Canadian well
This way the cost of heating oil has been reduced approximatively by 70%.

Improving my home's energy efficiency gives me the same revenue that I would get from investing in a bond at 2,5%. This performance will be reviewed upwards as the energy costs are increasing. Moreover, I benefit from a more confortable home and preserve the environment.

Energy consumption
Surface of energy reference : 318 m2
Index calculted energy expediture : 91 Mj/m2 meaning 25kWh/m2 per year (env. 2.5 l. of heating oil per m2/an)
Heating season could be reduced to : 4.5 months per year.
Project team : Christian Etienne
Building construction
Autorisation's deposition date : July 2008
Beginning : March 2009